The Capital Project and Construction (CP&C) group performs all construction and renovation work on campus by overseeing the work of contractors, consultants and PSU crews.

This work is performed on new or existing buildings related to structural, mechanical, electrical and architectural systems.

The CP&C group is also responsible for the planning, execution and management of all capital construction projects and improvements on campus. Basic cartography and demographic study also fall within this realm. Our group updates campus and University District maps and accommodates growth needs due to increasing student enrollment and utilization of campus facilities.

 

If you are interested in bidding opportunities at PSU please use the Oregon University System by clicking here or through their site http://www.ous.edu/about/bid

    Current Large Construction Projects:

    *Click on image or Project name for more information

     

    Life Sciences Collaborative Project

     
    Project Description: A collaborative effort between OHSU, OSU and PSU creating a state of the art facility for life sciences, research and teaching, plus a future home for part of PSU Chemistry and Biology Departments and OSU School of Pharmacy.
    Design Status: 99%
    Construction Status: 80%
    Status Description: In Construction
    Budget: $200,000,000
    Architect or Engineer: SERA/CO
    General Contractor: J.E. Dunn

    School of Business Remodel


    Project Description:Construction of a new addition to the North end of the building that will fully utilize the project site, create a new dramatic entrance to the School, and activate the building along Sixth venue. Modernization and upgrade of the existing structure.  (Design has not started yet, this is a preliminary image only)
    Design Status: 2%
    Construction Status: 0%
    Status Description: A & E Request For Proposals posted
    Budget: $57,000,000
    Architect or Engineer: TBD
    General Contractor: TBD
    Anticipated Start Date: Summer 2014

    Peter Stott Center Upgrade Including Viking Pavillion


    Project Description: Renovate and expand Peter Stott Center that includes 30,000 sf for student's advising, tutoring, studying classrooms and two arenas. (Design has not started yet, this is a preliminary image only)
    Design Status: 1%
    Construction Status: 0%
    Status Description: Drafting A/E RFP
    Budget: $57,000,000
    Architect or Engineer: TBD
    General Contractor: TBD
    Anticipated Start Date: TBD

     

    WHP Boiler Replacement




    Project Description: Demo and replaces WHP boiler's along with new steam and condensate piping. Associated re-piping in Tunnel and CH. Boilers & other equipment installed piping nearly complete.
    Design Status: 99%
    Construction Status: 83%
    Status Description: In Construction, Boiler Delivered
    Budget: $2,000,000
    Architect or Engineer: GHD & PSU
    General Contractor: Heinz Mechanical

     

    SB1 20 & 21 Microscope


    Project Description: Install of electron Microscope related instrument. Includes remodel of existing lab & storage area to a high-tech lab space. Work includes HVAC system install to accommodate equipment requirements. Waiting for equipment RFP completion before proceeding.
    Design Status:50%
    Construction Status: 0%
    Status Description: Request For Proposals
    Budget: $1,000,000
    Architect or Engineer: PSU
    General Contractor: PSU
    Anticipated Start Date: Fall 2013

    ML Extend Fire Protection


    Project Description: Increase fire protection system coverage in Millar Library.
    Design Status: 0%
    Construction Status: 0%
    Status Description: Predesign
    Budget: $1,000,000
    Architect or Engineer: TBD
    General Contractor: TBD
    Anticipated Start Date: Spring 2014

    Other Smaller Projects