Demolition - 2026/2027
Substantial completion slated for February 2027
Updates
- Staton took over building site Monday, November 2nd 2026.
- Interior demolition of Annex started Tuesday, November 3rd 2026.
- Interior demolition expected to take through November 2026.
- Exterior demolition expected to take December 2026 and January 2027.
Methods: Staton will use a combination of heavy equipment and hand-tool removal methods.
Construction status: Performing interior demolition.
General Contractor: Staton.
PSU Project Manager: Joseph Wuest (jwuest@pdx.edu)