New Housing Building

New Housing Building


Project Title: 
New Housing Building

The PSU New Housing Building will be a new residence hall designed to house more than 500 first-year students. The building will feature many amenities including a classroom, community rooms on all resident levels, a Student Concierge Center to support the PSU community and a private courtyard for the building residents.

Demolition of the Montgomery and Blackstone buildings is ongoing and anticipated to be complete by the end of 2026. Demolition activities are being conducted in accordance with all state and local regulations.

Please reach out to (503) 725-2349 with any project related questions or concerns.

Project Overview

Demolition Start Date
September 2026
 

Construction Start Date
Winter 2027

Construction End Date
Summer 2028

Project Manager
Urban Resources

Architect
GBD

General Contractor
Fortis Construction

Project Budget:
$85 Million