Project Description Renovation and expansion of the School of Business Administration into the Karl Miller Center. Construction of a new addition to the North end of the building will fully utilize the project site, create a new dramatic entrance to the School, and activate the ground floor with new Retail Spaces. Modernization and upgrade of the existing structure will meet the technical needs of students and improve sustainability.
 

Visit the School of Business Administration project page to learn more.

 
Watch the live feed of construction!

Design Status: 100%

Construction Status: 96%

Budget: $60,455,000

CPC Project Manager: Mark Fujii

Architect or Engineer: SRG + Behnisch

General Contractor: Skanska

Start Date: September 18, 2013

Substantial Completion: September 19, 2017

 