Other Projects

Fourth Avenue Building 22 OIT UPS Replacement

 
Project Description: Replaced (3) existing UPS units with (2) new UPS units and (2) new static switches configured in a manner that either or both UPS units can feed through either static switch. A preaction sprinkler system was called to prevent inadvertent damage to UPS.
Design Status: 99%
Construction Status: 97%
Status Description: Possible Starline Bus Meters to be added
Budget: $850,000
Architect or Engineer: Glumac
General Contractor: EC Company, Various

St. Helens Roof Replacement 


Project Description: Replace roof and provide seismic upgrade.Design proposal submitted to PSU Housing. Funding still being allocated. 

Design Status: 20%
Construction Status:0%
Status Description: Schematic Design Complete
Budget: $320,000
Architect or Engineer: PRC, VLMK
General Contractor: TBD
Anticipated Start Date: Summer 2014

Smith Memorial Student Union CAE-COL Renovation

Project Description: This project has been modified. $65,000 for design, construction and moves, from CH and MSQ to the 3rd Floor Mezzanine of SMSU. Some SMSU Library staff to be relocated to ML. Repair of ML from original project demo. Punch phase.
Design Status: 99%
Construction Status:95%
Status Description: Punchlist
Budget: $315,000
Architect or Engineer: PSU
General Contractor: Inline Construction

West Heating Plant Generator Install

Project Description:Install new emergency generator at the WHP. Only remaining work is testing once WHP Boiler Replacement Project Complete.
Design Status: 99%
Construction Status: 95%%
Status Description: Final Testing
Budget: $320,000
Architect or Engineer:Glumac
General Contractor: Design Electric

1% for Art Science Research & Teaching Center

Project Description: Installation of art at (2) building entrances.
Design Status: 90%
Construction Status:0%
Status Description: Creating Shop Drawings
Budget: $200,000
Architect or Engineer: Thom Faulders
General Contractor:Thom Faulders